How does a subcontractor request a price increase on a job that turned out bigger, and how do I get the client to approve it?

The subcontractor stops before going over the amount you authorized and submits a change request on the job: what they found, photos, the extra labor and materials, and a new total. Your coordinator checks it, adds your markup to get the client price, and sends it to the client as a proposal, either in the client's own platform (a ServiceChannel proposal or a Corrigo quote, which raises the NTE only once the client approves) or by a link the client signs. Only after the client approves do you raise the sub's purchase order to the new cost and tell them to proceed, so the sub's PO, the client's NTE and both invoices all match.

  • Two limits per job: the client's NTE (your price) and the sub's PO (your cost). A change request moves both, in that order.
  • The sub stops at their PO amount and asks. Work above it without a written approval is at the sub's risk.
  • The request needs photos, a reason, line items and a new total, not just a number.
  • Add markup on the sub's cost to get the client price. 30% markup is a 23% margin, not 30%.
  • Revise the sub's PO only after the client approves, then check both invoices against the new numbers.

Book your demo

A video call with our team

Number of employees

This is the process for priced, one-off service work. Large construction projects with schedules of values, retainage and multi-tier change events usually need a construction project tool as well.

Facts checked as of November 2026. Sources at the end of the page.

Step by step

How a subcontractor price increase works, step by step

The change request is a record on the job with its own status, not a phone call. It passes through three people: the sub, your coordinator and the client.

1. Every job carries two amounts

The client's not-to-exceed (NTE) is the most the client has authorized you to bill. The sub's purchase order is the most you have authorized the sub to bill you. Microsoft's Dynamics 365 Field Service models exactly this: a price NTE, the maximum work order price the customer accepts without a special approval process, and a cost NTE, the maximum cost you accept before you assign work to a vendor.

2. The sub stops before going over

On site, the sub finds the job is bigger: rotted subfloor under the leaking toilet, a second failed valve, three times the debris quoted. Before spending above their PO, they stop. ServiceChannel tells its providers the same: if a repair will exceed the NTE, they must request an increase before completing the work, and if parts will exceed it, a proposal must be submitted and approved before the parts are ordered.

3. The sub submits a change request on the job

From the job link or portal, the sub enters what they found, before photos, the extra labor hours, the extra materials with costs, a new total cost and how long the extra work takes. The job moves to a status such as Change requested. Nothing else changes yet.

4. Your coordinator reviews and prices it

The coordinator checks the photos against the scope, compares the extra labor and parts with your rate card for that sub, and either sends it back with a question or accepts it. Then your markup goes on top of the sub's cost to make the client price, plus any trip or return-visit charge your client contract allows.

5. The client gets a proposal for the increase

If the work came through the client's platform, the increase goes back there. ServiceChannel lets providers issue a proposal without an RFP to increase the NTE or change the scope of an existing work order. Corrigo's API takes a quote through PUT /api/workOrder/quoteSubmit with an amount and a reason; the NTE is not increased instantly, only after the customer approves. For a direct client, send a priced proposal by link with the sub's photos, and capture a signature and the approver's name.

6. On approval, the client NTE goes up

In Corrigo, an approved quote sets the work order's NTE amount equal to the quote amount. Store the new client NTE, the approval date and the approver on your job so the invoice check uses the right number.

7. Then the sub's PO is revised and they proceed

Only now does the sub's PO go up to the approved cost, and the sub gets a message to continue. If your accounting system holds the PO, update it there too. ApprovalMax's help for Xero and QuickBooks Online recommends a new, additional purchase order for the difference when only the amount has gone up.

8. Invoices are checked against the new numbers

The client invoice must be at or under the new NTE. Corrigo notes that some customers prevent an invoice above the NTE from being submitted, and others accept it and reject it later as too expensive. The sub's bill must be at or under the revised PO.

Failure modes

Why it goes wrong

The sub does the extra work first and asks later

The sub finishes, then sends an invoice for double the PO. The client never approved the increase, so you either absorb the difference or argue with your own sub. A fencing contractor with subcontractor crews told us it spends four days a week going back and forth on claims: what is this for, why are you claiming this, who approved this.

The request is a phone call

A facility maintenance coordinator that runs handyman, plumbing and remodel jobs for retail chains through subs asked us exactly this question because increases arrive by phone or text. Nobody records the photos, the reason or the number, so the client gets a vague email and asks for details, and a day is lost.

The sub sees the client price

If the sub's request and the client's proposal are the same document, the sub learns your price and markup, and sometimes your client's contact. The same coordinator was firm that subs must never see client pricing or a way to contact the client. Two documents, two amounts.

The PO is never updated

The client approves the increase, the job is done, and the sub's bill arrives above the old PO. Accounts payable holds it, the sub chases payment, and nobody can find who said yes. The approval lived in an email thread, not on the PO.

NTEs set too tight create the requests

ServiceChannel's own guidance says low NTEs stall work and increase overhead, and suggests setting them about 15 to 20% above historical invoice data for that issue type, then watching how often proposals are needed. If most jobs need an increase, the limit is wrong, not the subs.

Small extras with no route at all

An IT field engineer network told us a part-time tech who spends $30 on travel should be able to open a small request that the back office accepts or rejects. Without a route for small amounts, they are either waved through without a record or argued about at invoice time.

Options

Ways to do it

How each approach handles the sub's request and the client's approval, from the vendors' own documentation in November 2026. The question to ask of each: does the sub's request and the client's approval end up on one job, with both amounts updated?

ApproachWhat it doesWatch for
Phone, email and a spreadsheetThe sub calls, the coordinator emails the client, and someone updates the PO and the job sheet once the client replies.Fine for a handful of increases a month. Approvals get lost in inboxes, and nobody can show a client or a sub who approved what.
The client's facilities platform (ServiceChannel, Corrigo)The increase goes to the client as a proposal or quote against the work order. ServiceChannel providers can issue a proposal to increase the NTE or change the scope of an existing work order. In Corrigo, a quote can be submitted only once; to quote again, the customer must reject the existing quote, even if it was approved.This covers you and your client only. It does not collect the request from your sub or revise your PO to them, so you still need your own step underneath.
A labor marketplace (Field Nation)After assignment, a provider can submit a pay change request or an additional charge request, and every pay increase request must be approved or denied by the buyer. Field Nation's API says pay can only be updated before the work order reaches Work Done.Works for technicians hired through the marketplace. It handles your cost side only; the client approval still happens elsewhere.
A construction project tool (Procore)Procore calls purchase orders and subcontracts commitments, and a commitment change order alters the original agreement with the sub. The number of steps depends on whether the project uses a 1, 2 or 3 tier change order setup.Built for projects with a schedule of values. Heavy for hundreds of small reactive work orders a month.
An enterprise field service suite (Dynamics 365 Field Service)Price, cost, and price and cost margin NTEs, applied by customer, incident type or location. Workers see a warning as price or cost approaches or exceeds the NTE.Microsoft's docs say the work order can still be saved when the warning appears. The warning does not by itself route an increase to the client; that flow has to be built.
A change request step in your own system (Fieldproxy)The sub submits the increase with photos from a job link or the subcontractor portal, an approval step holds it for the coordinator, the client approves a separate priced proposal by link, and the sub's PO is revised on approval.Set up around your markup rules and clients, so bring your rate cards and client NTE rules. For platform work orders, the client still approves inside the client's platform.

Ask each vendor to show one job where a sub asked for more money: where the sub typed it, what the client saw, and how the sub's PO changed after the client said yes.

Worked example

A worked example

Say a retail client sends a work order to replace a leaking toilet with a $500 NTE. You dispatch a plumbing sub on a $380 PO. The numbers are an illustration, not a statistic.

On site, the sub pulls the toilet and finds the subfloor soft around the flange. They stop, take six photos, and submit a change request: 4 extra hours at $65, a sheet of plywood and fasteners at $90, and a new total cost of $730.

LineSub's cost (your PO)Client price (the NTE)
Original scope$380$500
Extra labor, 4 h at $65$260
Plywood and fasteners$90
New total cost$730
Client price at 30% markup on cost$949
After approvalPO revised to $730NTE raised to $949

Your coordinator checks the photos and the sub's hourly rate, then sends the client a proposal for $949 with the photos, through the client's platform. The sub never sees the $949. A markup of 30% on cost is a gross margin of $219 on $949, about 23%. If your rule is a 30% margin, the client price is $730 divided by 0.70, about $1,043. Decide which one your rate card means before anyone prices an increase.

The client approves the next morning. The NTE on your job becomes $949, the sub's PO becomes $730, and the sub gets a text to go ahead. Two weeks later the sub bills $730 and you invoice $949. Both match without anyone asking who approved what.

Had the sub finished first and billed $730 against a $380 PO, you would have been asking a client to approve work already done, and some clients would refuse.

Before you buy

What to check before you buy

Good signs

  • Each job holds the client's NTE and the sub's PO as two separate fields.
  • The sub can submit an increase from a phone, with photos, line items and a reason, without seeing your client's price.
  • The request has its own status and blocks the job from being closed or invoiced while it is open.
  • Markup or margin rules per client or trade fill in the client price, and a person can override them.
  • The client approves by link with a signature, or the increase is pushed to the client's platform as a proposal or quote.
  • Approval updates the NTE and the PO together, and both appear on the job's history with who and when.
  • Invoices and sub bills are checked against the new amounts before they go out or get paid.

Red flags

  • The increase is typed into a notes field.
  • The sub's request and the client's proposal are the same document.
  • The sub's PO can be edited by anyone with no record of the approval.
  • Subs need a paid seat to submit a request.
  • Nothing stops a sub's bill above the PO from being paid.

In Fieldproxy

Setting it up in Fieldproxy

Fieldproxy is set up around your process, so the statuses, markup rules and wording are yours. Settings marked e.g. are examples to change.

Two amounts on every job

Jobs carry the client's NTE and the sub's PO amount as their own fields. Work orders that arrive by email or PDF are read into jobs with the NTE filled in by the Document intelligence agent.

A change request form for the sub

Regular subs use the subcontractor portal; one-off subs get a job link that opens in the phone's browser. Both include a change request form (e.g. what you found, photos, extra hours, extra materials, new total) that moves the job to Change requested. Client pricing and contacts stay hidden from the sub; see hiding pricing from subcontractors.

An approval step for the coordinator

Approval workflows hold the request until the coordinator approves, returns or rejects it. A rule fills in the client price from the sub's cost (e.g. 30% markup, or a per-client rate card), and the Vision agent can check the photos show what the request describes.

A proposal the client approves

The client price goes on a proposal built from your custom estimates, with the sub's photos attached, and is sent by customer link for a signature. For ServiceChannel and Corrigo work, see managing those work orders in your own system.

Approval updates both amounts

When the client approves, the job's NTE and the sub's PO update together and the sub is told to proceed. Bills and invoices sync with QuickBooks or Xero (integrations).

Chasing and late approvals

The Watcher agent flags requests waiting too long (e.g. no client answer in 24 hours) and jobs whose spend passes the PO with no approved change. Autopilot drafts the reminder to the client as a card a person approves. One price per company with unlimited users, so subs and client approvers do not need seats; see pricing.

Contracts

Contract and legal notes

Commercial clients: the contract and the platform decide

For commercial work, your master service agreement and the client's platform rules decide whether work above the NTE gets paid. ServiceChannel's managed program also measures how long work orders sit in Proposal Approved status, with a 3 day goal, so a slow restart after approval counts against you.

California home improvement work

The California Contractors State License Board's consumer guide says that if the contract price needs to change, it must be done with a written change order that becomes part of the contract. If any of your subcontracted work is for homeowners, get the increase in writing and signed before the extra work starts.

Your subs: put the rule in the agreement

State in the subcontractor agreement that work above the PO is paid only with a written change approval on the job, and how long you have to answer. It makes the stop and ask step the sub's protection too.

How switching works

How switching to Fieldproxy works

We move your data over and set the system up to the way you already work. Fieldproxy replaces the old tool; it does not run alongside it.

  1. Bring two jobs that grew

    One where the sub asked first and one where they did not, with the client NTE, the sub's PO and both invoices.
  2. We set the amounts, the form and the markup rule

    NTE and PO fields, the sub's change request form, the coordinator approval, and the client price rule per client or trade.
  3. Subs and clients come across

    Subs, their rate cards, clients and their NTE rules move over in an assisted migration. Subs get the portal or job links, with no app to install.
  4. Run it on live jobs

    Start with one client and its subs, check every increase end to end for a week, then turn it on for the rest. Live within a day.

FAQ

Questions people ask

Can a subcontractor request a price increase on a job and route it to the client for approval?
Yes. The sub submits the increase on the job with photos and a new cost, your coordinator approves it and adds your markup, and the client approves a separate proposal at the client price. The sub never sees the client's price.
Should the sub stop work while the increase is approved?
Stop the extra work, not necessarily the visit. The sub can finish what is inside the PO, make the site safe, and return once the increase is approved. For an emergency, agree a rule with the client in advance, such as a phone approval recorded on the job.
Do I mark up the sub's increase or pass it through at cost?
Most service companies mark it up the same way as the original job, because coordinating the change is work. Check your client contract: some cap markup on subcontracted work, and some require the sub's quote to be attached.
What if the client rejects the increase?
The NTE and the sub's PO stay where they were. The sub finishes only the original scope or leaves the site safe, and the job closes at the original amounts. In Corrigo, a rejected quote lets you submit a new one.
Can the client approve without a login?
Yes, by a link that shows the proposal and the photos and takes a signature. Clients on ServiceChannel or Corrigo approve inside their own platform instead.
Should I edit the sub's purchase order or raise a second one?
Either works if the approval is recorded. Many finance teams prefer a second PO for the difference so the original stays as issued; ApprovalMax recommends that for amount increases in Xero and QuickBooks Online.
How do I handle small extras like a $30 travel charge?
Give small amounts their own route: below a threshold you set, the coordinator can approve inside the client's NTE headroom without going back to the client. Everything above it goes to the client.

Sources

Competitor details on this page come from the vendors' own pages and documentation, checked as of November 2026. Plans and prices change, so check the vendor's current page before you decide.

See it built on your workflow

Tell us how your jobs run today. We build a demo on your stages, forms and pricing before the call.